More than 400 projects are impressive proof of our performance.

Planning, manufacturing, programming, installation and commissioning innovative solutions from one source for:

  • Water supplies
  • Flood protection
  • Irrigation systems


Electrical equipment:

  • Customer advising to detailed planning
  • High-quality switchboard manufacturing
  • Pump control cabinets outdoor and indoor installation for every power range
  • Creating control and regulation software
  • Telecontrol systems for all conventional transmission methods
  • Process control systems for centrally regulating and monitoring systems
  • Web-based monitoring of process data – WebControl
  • Alert systems
  • Property protection systems
  • Delivery and commissioning of measurement technology components
  • Installation and wiring performed by experienced personnel
  • Commissioning along with operator training
  • Regular inspection and maintenance
  • Troubleshooting and resolution in case of a fault


Mechanical equipment:

  • Plant piping and modifications
  • Measurement technology
  • UV systems
  • Pumps
  • Drinking water power plant
  • Fittings

Creating system-specific regulation and control software:

  • PLC-based control and regulation software
  • On-site visualizations on color touch displays of any size
  • Telecontrol software incl. intermediate data storage
  • Alert system software
  • Process control systems for any system size
  • Web-based monitoring of plant data – WebControl

A big emphasis on customer service:

  • Troubleshooting
  • Maintenance work
  • Modernization suggestions
  • Repeat inspections pursuant to ÖVE/ÖNORM EN 50110-1 and ÖVE/ÖNORM E 8001-6-61 to 63

REFERENCE PROJECTS

Außerbraz water supply plant & drinking water power plant (expansion)
Construction period:
June 2015 to August 2015
Scope of assignment:
  • Telecontrol cabinets
  • Turbine control cabinets
  • Telecontrol system
  • Measurement technology
  • Process control system (ACC/PDC)
Danube flood protection Dürnstein
Construction period:
September 2014, remaining work in winter 2015
Scope of assignment:
  • Low-voltage systems
  • Electrical installation work
  • Measurement technology
  • Control and regulation system
  • Telecontrol system
  • Process control system (ACC/PDC)
Klausen-Leopoldsdorf water supply plant
Construction period:
June 2013 to March 2014
Scope of assignment:
  • Telecontrol cabinets
  • Pump control cabinets
  • Measurement technology
  • Fiber optic communication
  • Wireless transmission system (P-Tech)
  • Process control technology (ACC/PDC)
Serfaus water supply plant
Construction period:
September 2014 to February 2015
Scope of assignment:
  • Telecontrol cabinets
  • Telecontrol system (fiber optic communication)
  • Measurement technology
  • Process control technology (ACC/PDC)
St. Veit an der Gölsen water supply plant
Construction period:
April 2011 to March 2014
Scope of assignment:
  • Pump control cabinets
  • Measurement technology
  • Photovoltaic systems
  • Process control technology (ACC/PDC)
Strengen am Arlberg water supply plant
Construction period:
August 2013 to July 2014
Scope of assignment:
  • Telecontrol cabinets
  • Measurement technology
  • Telecontrol transmission system (UMTS/VPN)
  • Process control technology (ACC/PDC)
University of Innsbruck flood protection
Construction period:
September 2014 to September 2015
Scope of assignment:
  • Low-voltage systems
  • Electrical installation work
  • Measurement technology
  • Control and regulation system
  • On-site process control technology (ACC/WINCC)
Flood protection Völser Gießen
Construction period:
September 2014 to August 2015
Scope of assignment:
  • Low-voltage systems
  • Electrical installation work
  • Measurement technology
  • Control and regulation system
  • On-site visualization system